The timeline for construction is anticipated to span five years (2020-2025). It is divided into three phases:
-
Design: time needed to review concepts, produce construction documents, and receive authorization from the Board to release for bidding
-
Bid: time needed for prospective bidders to get drawings, estimate and submit bids for the design, and the construction team to analyze and formulate recommendations for Board approval
-
Build: time needed to award contracts, purchase materials, construct, and once completed, turn over the facility to the school district to occupy.