The Design phase at Countryside took place from December 2020-August 2021.
Build 220: Countryside Community Meeting from Barrington 220 School District on Vimeo. Click here to view the PDF presentation from the video.
The Bid phase at Countryside is took place from September 2021-November 2021. At the Nov. 2 Board of Education meeting, the Board approved bids for the Build 220 construction projects at Countryside Elementary and Roslyn Road Elementary. An estimated total of $13,384,828 will be spent at both schools, which includes all construction costs and non-construction items such as safety and security, furniture and technology. The bids for construction costs that the Board approved came in at $5,024,471 for both schools, which does not include roofing work.
The Build phase at Countryside is scheduled to take place from Summer 2022-December 2022. In addition to safety and security upgrades and general repairs/maintenance, key projects include: